Fixed Cost Accrual Task Field. This cost is independent of the tasks duration and of any costs of resources that could be assigned to it. The Fixed Cost Accrual field provides choices for how and when fixed costs are to be charged or accrued to the cost of a task.
This contains the sum of all task costs including the cost of work resources the amount that you may people for certain tasks the costs of materials that are being used and even any fixed costs associated with the project. Save to your account. Costs accrue as work is scheduled to occur and as actual work is reported.
Project will now schedule a 500 cost against the task Generate proofs at the tasks end date and the project will incur this cost when the task ends.
How Calculated When you enter a fixed cost for a task in a task sheet Microsoft Office Project enters the fixed cost in the timephased portion of the Task Usage view according to the accrual method you selected. MicrosoftOfficeProjectServerLibrary in MicrosoftOfficeProjectServerLibrarydll Syntax. Use the TaskFixedCostAccrual type to set the TASK_FIXED_COST_ACCRUAL property in the following objects. If you had set the Fixed.